Learn how to import project data directly from Microsoft Project
Prerequisites ✅
- An existing .mpp file
- An edison365 Project with a Schedule Table
Steps 📎
- The import option is found on the schedule table settings cog "Import a Project File".
- Clicking the "IMPORT" button will launch the file explorer to locate the mpp file.
- Selecting the .mpp file and clicking "Open" will initiate the data import.
- While the import is taking place the edison365 loading animation is seen on the settings cog.
- Once completed, the tasks from the .mpp file will appear in the tasks table.
- Close the settings cog and check the imported tasks have imported as expected, update any tasks as needed.
- Ensure the project save icon is completed before navigating away. (See the arrow above in the example, it has not saved yet.)
Tip: It is recommended to import the .mpp file in to an empty schedule tasks table.
Note: In the current version, the import is limited to 600 tasks in the .mpp file.
Data Mapping Details ➡️
The following data is mapped from the Microsoft .mpp file into the edison365 Schedule table:
Source MPP file field | Target edison365 schedule table field |
Task Name | Name |
Start | StartDate |
Finish | EndDate |
% Complete | PercentDone |
Work | Effort |
* Displayed in the Work field | Effort Unit |
Constraint Date | ConstraintDate |
Constraint Type | Constraint Type |
Ignore Resource Calendar | IgnoreResourceCalendar |
Milestone | IsMilestone |
Rollup | Rollup |
WBS | WBS |
Duration | Duration |
* Displayed in the Duration field | DurationUnit |
Type | SchedulingMode |
Task Mode | ManuallyScheduled |
Notes | Description |
Resource Names | AssignedResource |
Predecessor | Predecessor |
Successor | Successor |
Resource names that exist in the .mpp file are mapped to tasks in the edison365 Schedule table where the resource name from the .mpp file matches a resource name in the central edison365 Resource list.
The default calendar is also used from the imported data.
In a later release there will be an update where we will try to match the calendars in the .mpp file and edison365 instance by name and apply those.